Nine figures of real estate, run like an operation

Company-wide ownership of real estate and facilities at Lightmatter — over $100M in transactions negotiated and more than $10M of lab-equipped build-outs delivered in under two years, both under budget, alongside the IT and security organization.

Role
Head of IT, Security & Facilities
Company
Lightmatter — Mountain View, CA
Sector
Silicon photonics · AI compute
Timeframe
2024 – 2026
The challenge

A growing hardware company that needed real space, fast.

Photonics is a physical business — it needs labs, clean environments, and room to grow into. As Lightmatter scaled, real estate and facilities became a genuine constraint on the company, not a back-office afterthought.

Facilities was handed to Aaron deliberately, because of his operational background — a vote of confidence that the person who could build the IT and security org could also build the physical one. The mandate carried real capital behind it: over $100M in real estate transactions and more than $10M of construction, delivered while the company kept shipping — and delivered under budget.

Key workstreams

What the work actually was.

01

Company-wide ownership

Assumed control of all real estate and facilities across the organization, folding a physical operation into an already-broad technology mandate.

02

Over $100M in real estate transactions

Negotiated and closed more than $100M of real estate deals, aligning long-term site strategy with the company's growth curve.

03

$10M of build-outs, both under budget

Delivered over $10M of construction and fit-out — including purpose-built lab space — in under two years, with both projects landing under budget. Identified a further $67K in savings on the Mountain View build alone.

04

Multi-site delivery

Stood up and moved into sites across Boston, Mountain View, Toronto, and Palo Alto — including a 7,989 sq ft Toronto suite live in May 2026 — with the IT and network build-out delivered in lockstep so teams landed in working, lab-ready space.

05

Capital recovery and controls

Tracked $2.51M of the $2.54M entitled tenant-improvement reimbursement on the Boston project, reconciled directly with Finance and Facilities.

06

Technology and space as one program

Ran conference-room AV, structured cabling, switching, circuits, and network resiliency as part of the same delivery — so the building and the systems inside it came online together.

07

Facilities service management, automated

Brought Facilities onto the same AI-agent service desk built for IT — a large share of Facilities requests now resolve without a person touching them, one of the highest deflection rates of any queue in the company.

Results & impact

What it delivered.

$100M+Real estate transactions negotiated and closed
$10M+Build-outs delivered — both projects under budget
< 2 yrsTo deliver both projects end to end
$2.51MBoston tenant-improvement reimbursement recovered, of $2.54M entitled
4Sites delivered — Boston, Mountain View, Toronto, Palo Alto
$67KAdditional Mountain View build savings identified

“Facilities came to me because of the operations background. Over $100M in transactions and $10M of build-outs in under two years, both under budget — it is the same discipline as any build.”

Areas of impact

Four ways it mattered.

Scale

Nine figures of real estate transacted against real growth pressure.

Discipline

$10M of build-outs delivered under budget, twice.

Labs

Purpose-built environments for a physical, photonics business.

Execution

Sites and the systems inside them delivered as one program.